How Long Does a Bathroom Renovation Take?
A typical London family bathroom renovation takes about 7 to 12 working days on site. Small en-suites are quicker, wet rooms take longer, and materials lead times come on top.
A full renovation of a typical London family bathroom takes about 7 to 12 working days on site. A small en-suite or cloakroom can be quicker. A wet room takes longer, because the waterproofing has to cure before tiling. Tile and sanitaryware lead times are separate from site time, so allow for them before the first day on site.
These are typical timings from our bathroom refurbishment page, checked on 22 November 2026. Your own timetable is set after a survey and sent with the estimate.
How long does a bathroom renovation take?
On-site time depends mostly on the type of bathroom and how much changes behind the walls. The table sets out the four situations we see most.
| Type of job | Typical time on site | What drives it |
|---|---|---|
| Typical family bathroom, full refit | about 7 to 12 working days | Strip-out, pipework and cables, waterproofing, tiling, fitting, testing |
| Small en-suite or cloakroom | can be quicker | Less tiling and fewer fittings |
| Wet room or walk-in shower | takes longer | Floor built to a fall, tanked, drain fitted, tanking must cure before tiling |
| Layout changes, repairs found after strip-out | depends on what is found | New waste routes, replastering, rot, damp or old wiring |
Source: Plumbery bathroom refurbishment page. We give a range for the typical job because the honest answer is a range. A figure for your own bathroom comes only after the survey.
What happens during a bathroom renovation?
Knowing the order helps you understand where the days go. This is the sequence we follow.
- Survey. The room is measured, and the soil stack, waste falls, water pressure, electrics and ventilation are checked.
- Written estimate and timetable. Labour is charged at published hourly rates, with materials listed separately. A timetable comes with the estimate.
- Strip-out and first fix. The old suite, tiles and boards come out, and new supply, waste pipes and cables are run.
- Waterproofing and boarding. Boards and tanking go in around the shower and bath. Walls are plastered where they will not be tiled.
- Tiling. Floor and wall tiles are laid, with movement joints and silicone at changes of plane.
- Second fix and fitting. The toilet, basin, bath or tray, screen, taps, towel rail, lights, mirror and extractor fan are fitted and tested.
- Testing and handover. Pressure, leak and electrical tests are carried out, certificates are issued, and the room is cleaned and walked through with you.
The steps that cannot be hurried are waterproofing and tiling. Tanking has to cure before tiles go on, which is why wet rooms take longer. In our design process, waterproofing also gets a 24-hour flood test before tiling. The test exists to find a leak before tiles cover it.
What is included in the 7 to 12 days, and what is not?
Included in the on-site time:
- Strip-out and disposal
- First-fix plumbing and electrics
- Waterproofing, boarding and plastering
- Tiling
- Second fix, fitting and decorating work in the room
- Testing, certificates and handover
Not included in that figure:
- Lead times for tiles, sanitaryware and any special-order items
- The design stage, if you want the room drawn up first
- Time to resolve structural problems found after opening up, such as rot, damp, asbestos or substandard wiring
- Drawings, structural engineers, planning and party wall processes, where your project needs them
- Delays caused by access, parking or building rules, for example in a flat
What makes a bathroom renovation take longer?
- A wet room or walk-in shower. Building the floor to a fall, tanking, fitting a drain and tiling takes more steps than fitting a tray, and the tanking has to cure.
- Moving the toilet or soil pipe. The toilet needs a workable route to the soil stack with enough fall. Where gravity drainage is not possible, a macerator or pump can be used. We check this at the survey.
- New partitions, a new window or replastering. Each adds steps and drying or fitting time.
- Surprises. What is behind the old tiles is only known after strip-out. Structural problems are priced and scheduled separately.
- Late decisions. Colours, tiles and fittings should be chosen before work starts. Changing a tile after boards are up can stop the job.
- Missing materials. If you supply your own items, they must be on site before work starts, otherwise the start date moves.
How long before work can start?
Materials are ordered after the estimate is agreed, and work starts once everything has been delivered. So the real timeline is the survey, the estimate, the lead time on your tiles and suite, then the 7 to 12 working days on site.
Lead times vary by product, and we cannot give one figure that is true for every tile or suite in the country. Ask for lead times in writing when you choose products, and ask whether anything is made to order, because made-to-order items are the likeliest to delay the start.
If you want the bathroom designed first, allow for that stage as well. Our design service includes a home measure, a layout, a tile layout, a services drawing, a fittings list and two rounds of changes. Details are on the bathroom and kitchen design page. The design fee is credited in full against a Plumbery installation of £12,500 or more including VAT, if the build contract is signed within 6 months of the design being delivered.
Will you be without a toilet?
Not for the whole job, in most cases. In a home with one bathroom, the toilet is usually reconnected at the end of each working day where the layout allows. Work is planned to keep downtime short, and we discuss the arrangements at the survey.
Plan for the rest of the disruption yourself. Clear the room, agree a route for the workers, protect floors elsewhere and tell neighbours if you live in a flat. If you live in a leasehold flat, check your lease first, because it may require a licence for alterations. We can provide insurance and method details if a managing agent asks for them.
Do building regulations affect the timeline?
A like-for-like replacement usually does not need building regulations approval. Under Part P, a new circuit, a new consumer unit, or any addition or alteration to circuits in the zone around a bath or shower is notifiable. Adding a bathroom or changing its ventilation brings in Part F, and moving a toilet or adding drainage can need building control under Part H. The government explains when notification is required in Approved Document P.
Our electricians test the electrical work and issue the electrical installation certificate at handover; the estimate says how any notifiable work will be signed off. This is general information for homes in England, correct at the date shown, not advice for your property. Do not attempt notifiable electrical work yourself.
How can you keep the renovation on schedule?
- Choose everything before the estimate is signed. Tiles, suite, shower, taps, towel rail, lighting.
- Ask for the timetable in writing. It should be sent with the estimate.
- Confirm delivery before the start date. Everything needs to have arrived, including anything you are supplying.
- Keep the layout if time matters. Moving the toilet or switching to a wet room adds steps.
- Agree what happens if a problem turns up. The answer should be in the estimate, with how a change would be priced and scheduled.
- Be home or arrange access on day one. You provide access to the property, water and electricity.
How much does it cost?
A basic refit on the same layout starts from £3,850 including VAT. Typical London prices for fuller jobs are in how much a new bathroom costs in London, and the bathroom cost calculator gives a range for your room in a few minutes.
When you are ready, read about our process on the bathroom refurbishment page and book a survey. You then get a written estimate and a timetable. Plumbery LTD provides this service, so treat this guide as the view of a company that fits bathrooms. Our timings come from our own page, and we say where they are typical rather than promised.
FAQ
How long does it take to renovate a small bathroom or en-suite?
A small en-suite or cloakroom can be quicker than a typical family bathroom, which is about 7 to 12 working days. The exact time depends on the tiling, the fittings and what is found behind the old walls.
Why does a wet room take longer than a standard bathroom?
The floor has to be built to the correct fall, tanked, fitted with a drain and tiled. The tanking must cure before tiling, and the room is leak-tested before handover.
How long should I wait before the work starts?
That depends mainly on the lead time of your tiles and suite. Materials are ordered after you agree the estimate, and work starts once everything is delivered. Ask for lead times in writing before you commit to a product.
Will I have to move out during a bathroom renovation?
Usually not. In a one-bathroom home the toilet is generally reconnected at the end of each working day where the layout allows, and the work is planned to keep downtime short.
Can the toilet or shower be moved without adding much time?
Usually it can be moved, but it adds steps. The toilet needs a workable route to the soil stack with enough fall, or a macerator or pump where gravity drainage is not possible. This is checked at the survey and shows up in the timetable and the price.
Do you give a timetable?
Yes. A timetable is provided with the written estimate after the survey. It is the one to rely on, because the figures in this guide are typical, not a promise for your room.
By the Plumbery editorial team. Prices come from our published rates and cost calculators, include VAT unless stated, and were checked on . Every home is different, so we confirm the final price in a written quote after a survey.
Keep reading
More renovation guides
Kitchen Renovation Cost in London (2026 Guide)
A kitchen renovation in London costs from £6,000 for a small supplied-and-fitted job and about £13,200 to £56,800 for a full kitchen. What moves the price, and what to check in a quote.
Read the guideHow Much Does a New Bathroom Cost in 2026? London Prices
A new bathroom in London costs from £3,850 for a basic refit and about £9,200 to £27,600 for a full job. Here is what moves the price, what is included and how to read a quote.
Read the guide